This is the last day I will be working on the RV until next week. I want to be able to have all the holes closed up so that in the event it rains while I’m away from this project, I won’t have to worry about leaks. I installed the new hot water heater today, worked on the bumper area some, and put in the trim around the wheel wells. The counter for the sink is built, sink set in place with the new faucet. The refrigerator has arrived and is in place with the wooden end panel and cabinet doors below the sink refinished and hung. Patches have been made to cover unneeded service ports and additional damaged partitions. Urethane has been applied to the vanity top and shelf above the couch. The owner has been by and is pleased with the progress thus far.